A line of 11 bodymakers is installed on three un-isolated monolithic foundations. The neighbouring building, located about 40 meters away from the machines, was complaining about excessive vibrations being transmitted to their premises.
Addressing excessive vibrations being transmitted to building neighbouring Can Manufacturer
Poland
Project Overview
The Challenge
Farrat were called to carry out a vibration investigation to assess the situation and present potential mitigation solutions.
Measurements were taken on and off the foundations in the factory to determine the degree of isolation provided by the inertia blocks, and outside, between the plant and neighboring building to measure vibration propagation to the surroundings.
The Results
Full transmission from foundation to factory floor
Related Projects
Film, TV & Recording Studios BIMM Riverside: Manchester
Farrat supplied our CineFLOOR products to the new film school BIMM in Manchester.
Film, TV & Recording Studios West London Film Studios
West London Film Studios needed an acoustic isolation solution for its expansion, adding 90,000 of production...
Cinema REEL Cinemas: Marassi Galleria Mall
We worked with our regional partner UniGroup to deliver an acoustic isolation solution for the REEL Cinema...
Cinema Grand Cinemas: Al Khiran Mall
Farrat designed and supplied 8 brand new screens for the Grand Cinemas branch in Al Khiran Mall.
Hotels hub by Premier Inn: Shoreditch
hub by Premier Inn in Shoreditch needed an acoustic isolation solution to prevent sound transmission...
Film, TV & Recording Studios University of Chicester
Farrat delivered our CineFLOOR MAX solution to The Tech Park project on the University of Chicester's...
Challenge our engineers
Contact us now for an initial consultation.