A line of 11 bodymakers is installed on three un-isolated monolithic foundations. The neighbouring building, located about 40 meters away from the machines, was complaining about excessive vibrations being transmitted to their premises.
Addressing excessive vibrations being transmitted to building neighbouring Can Manufacturer
United Kingdom
Project Overview
The Challenge
Farrat were called to carry out a vibration investigation to assess the situation and present potential mitigation solutions.
Measurements were taken on and off the foundations in the factory to determine the degree of isolation provided by the inertia blocks, and outside, between the plant and neighboring building to measure vibration propagation to the surroundings.
The Results
Full transmission from foundation to factory floor
Ähnliche Projekte
Wohnen Ashley Road East, London
Bereitstellung einer feuerbeständigen tragende thermische Trennung für den Einsatz zwischen Balkonanschlüssen...
Universität Nottingham Trent
Das preisgekrönte 7-Millionen-Pfund-Projekt auf dem Clifton-Campus der Nottingham Trent University umfasste...
Wohnen Mohammed VI Tower Rabat, Morocco
The tallest tower in North Africa! TBF was used to thermally separate the façade from the reinforced...
20 Ropemaker Street London, UK
TBF wurde in verschiedenen 2D- und 3D-Formen und -Größen verwendet, um die von Josef Gartner entworfene...
AFRC / Strathclyde Uni
AFRC / Strathclyde Universität
Industrial Optimale Vibrationskontrolle zur Unterstützung der Verlagerung großer Maschinen
Isomat, Keilbefestigungen
Fordern Sie unsere Ingenieure heraus
Kontaktieren Sie uns jetzt für ein erstes Beratungsgespräch.