Queen Mary University Graduate Centre

United Kingdom
Main Contractor
Bouygues UK
Acoustic Consultant
Bickerdike Allen & Partners
Structural Engineer
BDP
Total Buiding SLS Load: 129,400 kN
113 Natural Rubber Laminated Acoustic bearings
Natural frequency of 8Hz at working loads
Each bearing was tested upto full ULS loads
Test Certificates issued for each bearing
Installation schedule for each bearing, shear key and lateral restraint assembly

The Challenge

The eight-storey facility is constructed with a 750 tonne steel frame and concrete cores, a brick facade and curtain wall system. It is located in very close proximity to a particularly shallow section of the Central Line which has train movements every few minutes throughout the day. In the interest of ensuring the best environment for users, the university decided to invest in vibration mitigation measures to eliminate disruptions.

The Solution

Early on (RIBA Stage D), Farrat collaborated with the client’s concept design team to provide advice and guidance on the vibration isolation strategy in order to achieve the acoustic requirements set out by the acoustic consultant Bickerdike Allen Partners (BAP) and the clients structural engineer. The building was to be a 8 storey steel structure, with no basement so the ground floor slab was supported directly by the pile caps.

BAP recommended that for buildings on piled foundations, an allowance had to be made to account for the assumed coupling loss that can arise between the ground and the pile of between 4 dB and 7 dB. Amplification factors of 6 dB were included in the calculations to account for the fact that steel frame building elements such as floors and ceilings will tend to amplify vibrations at their fundamental frequency as compared to those present in the building foundations.

Design

The design incorporates cast in-situ ground beams with the ground floor slab constructed using 250mm pre-cast planks and a 50mm topping. Farrat worked with BDP to develop and refine the structural and vibration isolation system design.

The process began with BDP issuing all the column and core loads to Farrat as un-factored dead and live loads (un-factored loads are important because the performance of the isolation system is dependent on the typical in-use loadings). Farrat then applied its precise performance prediction tools to design acoustic bearings for each location and returned a Bearing Performance Schedule (BPS) to BDP who converted their pin connection details into springs using the spring constants given in Farrat’s BPS.

Although the overall load of the building remained the same, in some locations this led to some re-distribution of loads within the structure. These loads were returned to Farrat to update the BPS and issue back to BDP.

Plan view GA of the foundations showing the position of the 3 stability cores.

In some locations the design team had to consider horizontal forces resulting from rotation within the ground beams originating from the positioning of the column above and the pile cap below. Initially this rotation was to be resisted using lateral restraints but BDP and Farrat established that they could overcome the effect through strategic placement of the bearings and in some cases splitting a single bearing into 2, 3 or 4 bearings to give rotational resistance.

The building included seven external V columns which spanned from pile cap level up to the underside of level 2. In these cases, the V shape of the column meant that the vertical load included a horizontal component in line with the V shape which had to be resisted using acoustic lateral restraints.

In the other axis the columns had to be designed to resist the potential for a vehicle impact. The design of the cores was similar but required a more in-depth analysis to design the bearings in order to eradicate tension and incorporate appropriate lateral restraints to resist wind and other notional horizontal loads.

Typical section of the building, isolation system and foundations.

Fabien Roca
Civil Works Manager Bouyges UK
Farrat has been very helpful during the design stage and very reliable on product delivery, which was critical for the progress of the project.

Design

This was then followed by a coordinated process between Farrat and BDP to finalise the design and layout of the core vertical and lateral isolation systems as well as the structural design of the pile caps and isolated raft slabs.

For the lift core, which was set at a lower level, where access was restricted once the upper isolated slab was cast, Farrat provided an Isomat Acoustic Floating Floor system to be constructed between the bearings to enable a flat slab to be cast where no access was feasible thereafter.

The majority of the subterranean outer perimeter of the building was in contact with existing, rigid structures either where ground beams were cast up against them or where the ground was back-filled up against it. In order to maintain the isolation performance of the building, Farrat’s Isofoam perimeter isolation material was used as a resilient acoustic barrier.

In total Farrat manufactured and supplied 113 Natural Rubber Laminated Acoustic bearings each with a natural frequencyof 8Hz at working loads.

Every bearing was designed, manufactured and tested up to full SLS load and in accordance with the applicable standard for building isolation bearings BS EN 1337-3 and a test certificate was issued for each bearing. Schedules were provided identifying which bearing, shear key or lateral restraint assembly was to be placed in each location.

Farrat supplied galvanised steel levelling plates and upper formwork plates enabling the pile caps to be cast with a ±35mm tolerance. Once the bearings were in position they were grouted using a high flow, non-shrink cementitious grout. The high capacity lateral restraint shear keys were also installed in the cores in the same way.

This process enabled Bouygues to construct the bearing installation into the flowing construction process, working from one end of the building to another with pile caps still being cast at one end whilst at the other the pre-cast ground floor was already being installed. Farrat visited the site once per week during the construction process to undertake detailed inspections as well as provide support and advice to the site team.

Oliver Farrell
CEO & Technical Director, Structural Building Vibration Isolation Systems Farrat Isolevel
A key principle of the entire design was to optimise the vibration isolation performance and make every detail easy and quick to construct with minimal risk.

Related Projects

Challenge our engineers

Contact us now for an initial consultation.

Contact Us